A supplier who furnished control units for a private office building has not been paid. Which legal remedy lets the supplier place a claim against the improved property itself?

Exactly one answer is correct.

Show solution

Correct answer to question 1031

  • B: A mechanic's lien

Explanation

On private projects, unpaid contractors and suppliers can usually file a mechanic's (construction) lien against the property, subject to state notice deadlines. On public projects that remedy is replaced by the payment bond.