Question 1029 of 243 · NICET Fire Alarm Systems Level IV
On a percentage of completion job, you have billed 60 percent of the contract value while costs incurred represent 48 percent of the estimated total cost. How is the job reported on the work in progress schedule?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1029
- D: Overbilled, meaning billings run ahead of earned revenue
Explanation
Earned revenue follows the cost based percent complete of 48 percent. Billing 60 percent means the company has collected ahead of the work, which is an overbilling and a liability on the balance sheet. Heavy overbilling can hide a job that is running over budget.
More questions: Installation, Planning and Maintenance Management
- 1030The owner asks your field crew to add 14 speakers in a new conference wing that is not in the contract scope. What should the project manager do before the crew starts the extra work?
- 1031A supplier who furnished control units for a private office building has not been paid. Which legal remedy lets the supplier place a claim against the improved property itself?
- 1032Which type of insurance covers medical costs and lost wages for a fire alarm technician who is injured falling from a ladder on the job?
- 1033A design department manager reviews staffing. Which credential does NFPA 72 list as one way for a fire alarm system designer to show qualification?
- 1034At the end of a new building project, which item is required at the completion of a new fire alarm installation in addition to record drawings and site-specific software?
- 1035When should spot-type smoke detectors normally be installed in a building under construction?