Question 1029 of 243 · NICET Fire Alarm Systems Level IV

On a percentage of completion job, you have billed 60 percent of the contract value while costs incurred represent 48 percent of the estimated total cost. How is the job reported on the work in progress schedule?

Exactly one answer is correct.

Show solution

Correct answer to question 1029

  • D: Overbilled, meaning billings run ahead of earned revenue

Explanation

Earned revenue follows the cost based percent complete of 48 percent. Billing 60 percent means the company has collected ahead of the work, which is an overbilling and a liability on the balance sheet. Heavy overbilling can hide a job that is running over budget.