Question 1030 of 243 · NICET Fire Alarm Systems Level IV

The owner asks your field crew to add 14 speakers in a new conference wing that is not in the contract scope. What should the project manager do before the crew starts the extra work?

Exactly one answer is correct.

Show solution

Correct answer to question 1030

  • D: Obtain a signed change order that defines scope, price and schedule impact

Explanation

Changes in scope should be documented in a written change order signed by the authorized party before work proceeds. Verbal approvals and after the fact billing are common sources of unpaid work and disputes. AHJ approval covers code compliance, not contract scope or price.