Question 1030 of 243 · NICET Fire Alarm Systems Level IV
The owner asks your field crew to add 14 speakers in a new conference wing that is not in the contract scope. What should the project manager do before the crew starts the extra work?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1030
- D: Obtain a signed change order that defines scope, price and schedule impact
Explanation
Changes in scope should be documented in a written change order signed by the authorized party before work proceeds. Verbal approvals and after the fact billing are common sources of unpaid work and disputes. AHJ approval covers code compliance, not contract scope or price.
More questions: Installation, Planning and Maintenance Management
- 1031A supplier who furnished control units for a private office building has not been paid. Which legal remedy lets the supplier place a claim against the improved property itself?
- 1032Which type of insurance covers medical costs and lost wages for a fire alarm technician who is injured falling from a ladder on the job?
- 1033A design department manager reviews staffing. Which credential does NFPA 72 list as one way for a fire alarm system designer to show qualification?
- 1034At the end of a new building project, which item is required at the completion of a new fire alarm installation in addition to record drawings and site-specific software?
- 1035When should spot-type smoke detectors normally be installed in a building under construction?
- 1036A building owner asks whether an existing fire alarm system must be upgraded to the newly adopted NFPA 72 edition. Absent other requirements, what is the general rule?