At the acceptance test for a new voice evacuation system, the contractor should already have completed which step?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1043
- C: A full pretest of all devices and functions, with any deficiencies corrected
Explanation
The installing contractor tests 100 percent of the system before calling for the acceptance test, so the witnessed test confirms a working system. Discovering basic wiring or programming faults in front of the AHJ wastes time and often requires a paid retest.
More questions: Installation, Planning and Maintenance Management
- 1044A cost report shows a job is 50 percent complete, with 62,000 dollars spent against a 110,000 dollar total cost budget. What is the projected cost at completion if the overrun rate continues?
- 1045Which business record should a fire alarm department manager review to compare the estimated and actual labor hours for each completed project?
- 1046A building owner asks why the fire alarm ITM contract must also cover the interface relays for door release and fan shutdown. What is the best explanation?
- 1047When a building has several interconnected fire protection systems and is a high-rise, how often does the IFC require integrated testing in accordance with NFPA 4?
- 1048A department manager wants to cut costs by allowing an uncertified helper to perform the annual testing of a hospital system alone. Which NFPA 72 principle does this conflict with?
- 1049A new owner of a partly renovated building cannot find documentation for the existing system. Which step should a senior technician take first when evaluating it for a repair or replace decision?