Question 1043 of 243 · NICET Fire Alarm Systems Level IV

At the acceptance test for a new voice evacuation system, the contractor should already have completed which step?

Exactly one answer is correct.

Show solution

Correct answer to question 1043

  • C: A full pretest of all devices and functions, with any deficiencies corrected

Explanation

The installing contractor tests 100 percent of the system before calling for the acceptance test, so the witnessed test confirms a working system. Discovering basic wiring or programming faults in front of the AHJ wastes time and often requires a paid retest.