Question 1044 of 243 · NICET Fire Alarm Systems Level IV
A cost report shows a job is 50 percent complete, with 62,000 dollars spent against a 110,000 dollar total cost budget. What is the projected cost at completion if the overrun rate continues?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1044
- D: 124,000 dollars
Explanation
If 62,000 dollars bought 50 percent of the work, the full job projects to 62,000 divided by 0.50, or 124,000 dollars. That is a 14,000 dollar overrun that should trigger a review of labor productivity or scope changes.
More questions: Installation, Planning and Maintenance Management
- 1045Which business record should a fire alarm department manager review to compare the estimated and actual labor hours for each completed project?
- 1046A building owner asks why the fire alarm ITM contract must also cover the interface relays for door release and fan shutdown. What is the best explanation?
- 1047When a building has several interconnected fire protection systems and is a high-rise, how often does the IFC require integrated testing in accordance with NFPA 4?
- 1048A department manager wants to cut costs by allowing an uncertified helper to perform the annual testing of a hospital system alone. Which NFPA 72 principle does this conflict with?
- 1049A new owner of a partly renovated building cannot find documentation for the existing system. Which step should a senior technician take first when evaluating it for a repair or replace decision?
- 1050On a large commissioning project, what is the main role of the commissioning authority (CxA)?