A cost report shows a job is 50 percent complete, with 62,000 dollars spent against a 110,000 dollar total cost budget. What is the projected cost at completion if the overrun rate continues?

Exactly one answer is correct.

Show solution

Correct answer to question 1044

  • D: 124,000 dollars

Explanation

If 62,000 dollars bought 50 percent of the work, the full job projects to 62,000 divided by 0.50, or 124,000 dollars. That is a 14,000 dollar overrun that should trigger a review of labor productivity or scope changes.