Question 1058 of 243 · NICET Fire Alarm Systems Level IV
At substantial completion of a fire alarm project, what condition normally applies?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1058
- D: The owner can use the work for its intended purpose, with only minor punch list items left
Explanation
Substantial completion means the owner can occupy or use the work as intended. It often starts the warranty, shifts some responsibilities to the owner and allows release of part of the retainage. Final completion follows when the punch list is closed.
More questions: Installation, Planning and Maintenance Management
- 1059The specification requires owner training on the new voice evacuation system. What should the project manager deliver to show compliance?
- 1060A specification asks the contractor to turn over spare devices equal to 2 percent of each installed device type. What is this deliverable usually called?
- 1061How often must speakers and other audible notification appliances be functionally tested in an ITM program?
- 1062A smoke detector is located above a production line that can only be shut down safely during a planned plant outage. How does NFPA 72 treat testing of devices in such inaccessible areas?
- 1063An owner with a large campus wants to change some test frequencies based on documented device reliability. What does NFPA 72 allow?
- 1064A generator that complies with NFPA 110 is installed as the secondary supply for a fire alarm system. What battery capacity is still required at the control unit?