Before installing devices, why must the shop drawings for a new system normally be approved?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1068
- A: It confirms design and equipment before installation and avoids costly rework
Explanation
Shop drawings show what will be installed and where. Installing before approval risks tearing out work if the reviewer or the AHJ requires changes. Many jurisdictions also require approved plans before a permit is issued.
More questions: Installation, Planning and Maintenance Management
- 1069A fire alarm system must recall elevators, close smoke dampers, release doors and shut down air handlers. Which coordination tool should be agreed with the mechanical, elevator and door hardware trades early in the project?
- 1070A company is invited to bid a design build fire alarm upgrade. What is the most important step before preparing the price?
- 1071In a proposal for a retrofit, why should the contractor list clarifications and exclusions?
- 1072Which federal law requires contractors on federally funded construction contracts over 2,000 dollars to pay locally prevailing wages?
- 1073Which federal law requires performance and payment bonds on federal construction contracts above the set threshold?
- 1074How long must an employer keep the OSHA Form 300 injury and illness log?