Question 1067 of 243 · NICET Fire Alarm Systems Level IV

Which item should a fire alarm project manager order immediately after contract award because its lead time often controls the schedule?

Exactly one answer is correct.

Show solution

Correct answer to question 1067

  • B: Configured equipment such as networked panels, amplifiers and signal boosters

Explanation

Engineered or configured equipment can take weeks or months to build and ship, so it is a long lead item. Commodity materials are stocked locally. Procurement of long lead items often needs approved submittals, so those are prioritized as well.