Question 1097 of 243 · NICET Fire Alarm Systems Level IV

Which statement about the relationship between the fire alarm contractor and the engineer of record is typically true on a design bid build project?

Exactly one answer is correct.

Show solution

Correct answer to question 1097

  • B: The contractor submits shop drawings for the engineer's review

Explanation

In design bid build, the engineer prepares the design, and the contractor prepares shop drawings that the engineer reviews for conformance. Changes go through submittals or RFIs. The building official, not the engineer, issues the certificate of occupancy.