Correct answer to question 1038
- D: On-site, in nonvolatile, nonrewritable form
Explanation
NFPA 72 requires a copy of the site-specific software to be stored on-site in nonvolatile, nonerasable, nonrewritable memory, such as a write-once disc. This allows the program to be restored if the panel memory is lost or the contractor changes.
More questions: Installation
- 1039What is the typical format NFPA 72 suggests for presenting the sequence of operations in shop drawings and record documents?
- 1040When is the record of completion for a new fire alarm system prepared and provided?
- 1041During a site visit you discover an electrician has relocated six smoke detectors to avoid new ductwork, and the approved shop drawings no longer match. What is the correct Level III response?
- 1042What does the term as-built drawings, or record drawings, mean in the closeout package?
- 1043Before field devices are connected, your crew plans to test new cable runs with an insulation resistance tester. What is the main precaution?
- 1044Which of the following must be confirmed for two-wire smoke detectors connected to a conventional initiating device circuit?