Question 1041 of 297 · NICET Fire Alarm Systems Level III

During a site visit you discover an electrician has relocated six smoke detectors to avoid new ductwork, and the approved shop drawings no longer match. What is the correct Level III response?

Exactly one answer is correct.

Show solution

Correct answer to question 1041

  • D: Check the new locations against code, revise the drawings, and resubmit as required

Explanation

Field changes have to be checked against code and documented, and deviations from approved plans usually require resubmittal to the AHJ. The record drawings must reflect what is actually installed, so changes must be captured as they happen, not reconstructed at closeout.

Next to question ›