Before field devices are connected, your crew plans to test new cable runs with an insulation resistance tester. What is the main precaution?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1043
- B: Isolate all devices and the control unit so the test voltage cannot damage them
Explanation
Insulation resistance testers apply several hundred volts or more to find leakage and grounds. Fire alarm electronics in devices and the control unit can be damaged, so cable testing is done before connection, or with all equipment isolated.
More questions: Installation
- 1044Which of the following must be confirmed for two-wire smoke detectors connected to a conventional initiating device circuit?
- 1045Lead-acid batteries for the fire alarm system are delivered to the site. Which marking must the batteries carry?
- 1046A ceiling smoke detector on the drawings lands 2 ft from a supply air diffuser. What is the minimum distance you should direct the installer to maintain?
- 1047A spot smoke detector must be mounted on a sidewall because the ceiling is inaccessible. Where must it be placed?
- 1048An installer mounts a spot heat detector on a wall. Which location complies with NFPA 72?
- 1049In a room with a peaked ceiling, where should the first row of spot smoke detectors be placed?