Question 1054 of 297 · NICET Fire Alarm Systems Level III

During acceptance testing, how do you verify ground fault monitoring on each circuit?

Exactly one answer is correct.

Show solution

Correct answer to question 1054

  • C: Connect a ground to the circuit and confirm the trouble signal, then restore it

Explanation

Ground fault detection is tested by introducing a ground on each monitored circuit and confirming the control unit annunciates a trouble condition. Removing a device tests open circuit supervision, not ground fault detection.