Question 1058 of 297 · NICET Fire Alarm Systems Level III
Your project specifies a listed standby generator as part of the secondary supply. Under NFPA 72, what minimum battery capacity is still needed?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1058
- A: Enough to run the system for 4 hours
Explanation
Where an automatic starting generator meeting the code is used, NFPA 72 still requires storage batteries, but with capacity for 4 hours of operation instead of the full 24 hours. The batteries carry the system through generator start and transfer and any short outage.
More questions: Installation
- 1059Which items does NFPA 72 list as part of the record documentation turned over to the owner at completion?
- 1060How long must the fire alarm record documentation (record drawings, record of completion, sequence of operation) be kept?
- 1061What qualification does NFPA 72 list as acceptable for persons who prepare fire alarm system plans and specifications?
- 1062Who must be able to show evidence of their qualifications to the AHJ on a fire alarm project?
- 1063Under the IBC, what is the maximum floor area of a single fire alarm zone in a building that requires zoning?
- 1064How does NFPA 70 require fire alarm circuits to be identified in the field?