Question 1083 of 297 · NICET Fire Alarm Systems Level III

On a project where the AHJ requires a fire watch during the cutover from the old system to the new one, who is normally responsible for providing it?

Exactly one answer is correct.

Show solution

Correct answer to question 1083

  • A: The building owner or owner's representative, unless the contract assigns it otherwise

Explanation

The owner is responsible for the building's fire safety, including interim measures such as fire watches during impairments. Contracts sometimes assign the fire watch to the contractor, so the Level III must read the contract and confirm who provides it before the cutover begins.

Next to question ›