Question 1083 of 297 · NICET Fire Alarm Systems Level III
On a project where the AHJ requires a fire watch during the cutover from the old system to the new one, who is normally responsible for providing it?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1083
- A: The building owner or owner's representative, unless the contract assigns it otherwise
Explanation
The owner is responsible for the building's fire safety, including interim measures such as fire watches during impairments. Contracts sometimes assign the fire watch to the contractor, so the Level III must read the contract and confirm who provides it before the cutover begins.
More questions: Installation
- 1084A technician sets the panel to bypass the entire third floor while the ceiling contractor works there. Which control does the Level III need to ensure?
- 1085Which situation requires the installing contractor to perform reacceptance testing?
- 1086What is the purpose of the commissioning or acceptance test report signed at the end of the project?
- 1087A field change adds a new corridor with no manual boxes or notification on the approved plans. Which document change must the Level III make sure is completed?
- 1088Which statement correctly describes the AHJ's role during the acceptance test?
- 1089Before the final acceptance test, who should receive training on operating the fire alarm system?