Question 1087 of 297 · NICET Fire Alarm Systems Level III

A field change adds a new corridor with no manual boxes or notification on the approved plans. Which document change must the Level III make sure is completed?

Exactly one answer is correct.

Show solution

Correct answer to question 1087

  • B: Revised shop drawings, calculations, and sequence of operations, submitted for approval

Explanation

Additions alter coverage, circuit loading, and battery capacity, so drawings and calculations must be revised and usually resubmitted. The record documents must reflect the final installation at closeout.