Question 2030 of 297 · NICET Fire Alarm Systems Level III

Where testing personnel leave a system with an uncorrected deficiency at the end of a visit, what should the Level III service manager require?

Exactly one answer is correct.

Show solution

Correct answer to question 2030

  • D: Written notice to the owner describing the deficiency and the impairment status

Explanation

Deficiencies that are not fixed during the visit must be reported to the owner in writing so the owner can act and arrange interim measures where needed. NFPA 72 sets a short time frame for this notice when the condition is an impairment.