Under AIA A201, how long after Substantial Completion must the Contractor generally correct work found not to conform?

Exactly one answer is correct.

Show solution

Correct answer to question 4025

  • D: One year

Explanation

A201 12.2.2 sets a one-year correction period after Substantial Completion, during which the Contractor must correct nonconforming work promptly after written notice. This is separate from statutory warranty periods.