Question 4025 of 297 · NICET Fire Alarm Systems Level III
Under AIA A201, how long after Substantial Completion must the Contractor generally correct work found not to conform?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4025
- D: One year
Explanation
A201 12.2.2 sets a one-year correction period after Substantial Completion, during which the Contractor must correct nonconforming work promptly after written notice. This is separate from statutory warranty periods.
More questions: Management and Supervision
- 4026Under AIA A201, how soon must a Claim be made after the claimant first recognizes the condition giving rise to it?
- 4027Under AIA A201, what should the Contractor do on discovering an error between the drawings and specifications?
- 4028Under AIA A201, what does Substantial Completion mean?
- 4029A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?
- 4030A project manager prepares a bid for a fire alarm installation. Which item is most essential to include from the specification?
- 4031Which estimate component covers costs like insurance, office rent, and accounting that are not tied to a single job?