Question 4024 of 297 · NICET Fire Alarm Systems Level III

Under AIA A201, the Architect orders a minor change in the work that does not affect cost or time. What is this called?

Exactly one answer is correct.

Show solution

Correct answer to question 4024

  • C: A minor change order

Explanation

A201 7.4 lets the Architect order minor changes that do not involve an adjustment in Contract Sum or Contract Time and are consistent with the intent of the Contract Documents.

Next to question ›