Question 1014 of 243 · NICET Fire Alarm Systems Level IV

A fire alarm contractor agrees to install a high-rise voice system for a fixed total price regardless of the actual cost. Which contract type is this, and who carries the risk of cost overruns?

Exactly one answer is correct.

Show solution

Correct answer to question 1014

  • B: A lump sum contract, with the contractor carrying the risk

Explanation

Under a lump sum (stipulated sum) contract the price is fixed, so higher than estimated costs reduce the contractor's profit. Cost plus and time and materials contracts shift the cost risk to the owner, which is why owners usually require more cost reporting under them.