Question 1014 of 243 · NICET Fire Alarm Systems Level IV
A fire alarm contractor agrees to install a high-rise voice system for a fixed total price regardless of the actual cost. Which contract type is this, and who carries the risk of cost overruns?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1014
- B: A lump sum contract, with the contractor carrying the risk
Explanation
Under a lump sum (stipulated sum) contract the price is fixed, so higher than estimated costs reduce the contractor's profit. Cost plus and time and materials contracts shift the cost risk to the owner, which is why owners usually require more cost reporting under them.
More questions: Installation, Planning and Maintenance Management
- 1015An owner wants to pay the contractor's actual costs plus a fee, but with a ceiling the price cannot exceed. Which contract arrangement fits?
- 1016A campus retrofit is priced at a fixed amount per installed device because the final device count is not known at bid time. Which contract type is this?
- 1017The general contractor withholds 10 percent of each progress payment from the fire alarm subcontractor until the project is accepted. What is this withheld money called?
- 1018A contract states that the contractor will owe the owner 1,500 dollars for each calendar day the fire alarm acceptance test is late. What is this provision called?
- 1019Which bond protects the owner if the fire alarm contractor fails to complete the work according to the contract?
- 1020A supplier of fire alarm devices has not been paid by the electrical contractor. Which bond on a public project protects that supplier?