A campus retrofit is priced at a fixed amount per installed device because the final device count is not known at bid time. Which contract type is this?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1016
- D: A unit price contract
Explanation
Unit price contracts pay a set rate per unit installed, which suits work where quantities are uncertain. The final contract value equals the unit rate times the verified quantity.
More questions: Installation, Planning and Maintenance Management
- 1017The general contractor withholds 10 percent of each progress payment from the fire alarm subcontractor until the project is accepted. What is this withheld money called?
- 1018A contract states that the contractor will owe the owner 1,500 dollars for each calendar day the fire alarm acceptance test is late. What is this provision called?
- 1019Which bond protects the owner if the fire alarm contractor fails to complete the work according to the contract?
- 1020A supplier of fire alarm devices has not been paid by the electrical contractor. Which bond on a public project protects that supplier?
- 1021In a critical path schedule for a high-rise fire alarm installation, what characterizes the critical path?
- 1022An activity in your project schedule has an early start of day 12 and a late start of day 19. How much total float does it have?