An owner wants to pay the contractor's actual costs plus a fee, but with a ceiling the price cannot exceed. Which contract arrangement fits?

Exactly one answer is correct.

Show solution

Correct answer to question 1015

  • A: Cost plus fee with a guaranteed maximum price (GMP)

Explanation

A GMP contract reimburses actual costs plus a fee but caps the owner's total. Costs above the cap are absorbed by the contractor, and savings below it are often shared. A plain lump sum has no cost reimbursement at all.