Question 1037 of 243 · NICET Fire Alarm Systems Level IV
A service sales manager is preparing an RFP response for the annual testing of a 300 building portfolio. Which item should drive the labor estimate most directly?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1037
- C: The device counts and test frequencies for each building
Explanation
ITM labor scales with what must be tested and how often, which comes from device inventories and the frequencies in Chapter 14. Flat averages and floor area ignore dense systems such as hospitals or high-rise voice systems and lead to unprofitable bids.
More questions: Installation, Planning and Maintenance Management
- 1038Your company is replacing an obsolete control unit but keeping the existing conventional 2-wire smoke detectors. What must be confirmed before the new unit is ordered?
- 1039When a fire alarm contractor's project manager plans a large project, why is a schedule of values submitted early in the job?
- 1040A project manager is told a key activity on the critical path will finish 5 days late. Which response directly protects the project completion date?
- 1041Which closeout item gives the owner the narrative description of the system, operator instructions and the procedures for routine maintenance and testing?
- 1042A construction manager asks when the fire alarm contractor's warranty period normally starts. What is the most common contract answer?
- 1043At the acceptance test for a new voice evacuation system, the contractor should already have completed which step?