What must the record drawings delivered at closeout reflect?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1054
- A: The actual installed locations of equipment, devices and wiring, including field changes
Explanation
Record (as-built) drawings document the system as actually installed so that future service, testing and changes can be planned. Showing design intent where the field installation differs makes the drawings misleading.
More questions: Installation, Planning and Maintenance Management
- 1055Your field crew relocated 18 strobes during construction to avoid ductwork. Who is normally responsible for showing these changes on the record drawings?
- 1056A project manager wants the field changes captured accurately for record drawings. Which practice works best?
- 1057Which of these items is normally part of the fire alarm closeout package delivered to the owner?
- 1058At substantial completion of a fire alarm project, what condition normally applies?
- 1059The specification requires owner training on the new voice evacuation system. What should the project manager deliver to show compliance?
- 1060A specification asks the contractor to turn over spare devices equal to 2 percent of each installed device type. What is this deliverable usually called?