Question 1053 of 243 · NICET Fire Alarm Systems Level IV

Before the integrated test of a high-rise, what should have been completed for each individual system, such as the fire alarm, sprinkler and smoke control systems?

Exactly one answer is correct.

Show solution

Correct answer to question 1053

  • D: Each system's own acceptance testing in accordance with its installation standard

Explanation

Integrated testing assumes each system already works on its own. The fire alarm is tested to NFPA 72, sprinklers to NFPA 13 and so on, and the integrated test then checks the cross system responses.