Before the integrated test of a high-rise, what should have been completed for each individual system, such as the fire alarm, sprinkler and smoke control systems?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1053
- D: Each system's own acceptance testing in accordance with its installation standard
Explanation
Integrated testing assumes each system already works on its own. The fire alarm is tested to NFPA 72, sprinklers to NFPA 13 and so on, and the integrated test then checks the cross system responses.
More questions: Installation, Planning and Maintenance Management
- 1054What must the record drawings delivered at closeout reflect?
- 1055Your field crew relocated 18 strobes during construction to avoid ductwork. Who is normally responsible for showing these changes on the record drawings?
- 1056A project manager wants the field changes captured accurately for record drawings. Which practice works best?
- 1057Which of these items is normally part of the fire alarm closeout package delivered to the owner?
- 1058At substantial completion of a fire alarm project, what condition normally applies?
- 1059The specification requires owner training on the new voice evacuation system. What should the project manager deliver to show compliance?