A project manager wants the field changes captured accurately for record drawings. Which practice works best?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1056
- C: Keep a marked up drawing set on site and update it as changes are made
Explanation
Field marked drawings updated in real time are the reliable source for record drawings. Panel addresses do not show physical locations or wiring routes, and memory based reconstruction misses changes.
More questions: Installation, Planning and Maintenance Management
- 1057Which of these items is normally part of the fire alarm closeout package delivered to the owner?
- 1058At substantial completion of a fire alarm project, what condition normally applies?
- 1059The specification requires owner training on the new voice evacuation system. What should the project manager deliver to show compliance?
- 1060A specification asks the contractor to turn over spare devices equal to 2 percent of each installed device type. What is this deliverable usually called?
- 1061How often must speakers and other audible notification appliances be functionally tested in an ITM program?
- 1062A smoke detector is located above a production line that can only be shut down safely during a planned plant outage. How does NFPA 72 treat testing of devices in such inaccessible areas?