Question 1055 of 243 · NICET Fire Alarm Systems Level IV
Your field crew relocated 18 strobes during construction to avoid ductwork. Who is normally responsible for showing these changes on the record drawings?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1055
- D: The installing fire alarm contractor
Explanation
The installing contractor tracks field changes, usually through a marked up drawing set kept on site, and turns them into record drawings at closeout. A Level IV manager should require crews to mark changes daily rather than reconstruct them at the end.
More questions: Installation, Planning and Maintenance Management
- 1056A project manager wants the field changes captured accurately for record drawings. Which practice works best?
- 1057Which of these items is normally part of the fire alarm closeout package delivered to the owner?
- 1058At substantial completion of a fire alarm project, what condition normally applies?
- 1059The specification requires owner training on the new voice evacuation system. What should the project manager deliver to show compliance?
- 1060A specification asks the contractor to turn over spare devices equal to 2 percent of each installed device type. What is this deliverable usually called?
- 1061How often must speakers and other audible notification appliances be functionally tested in an ITM program?