Question 1066 of 243 · NICET Fire Alarm Systems Level IV

Your network shows two technicians needed in week 6 and seven in week 7 for the same project. What scheduling technique smooths these peaks within available float?

Exactly one answer is correct.

Show solution

Correct answer to question 1066

  • B: Resource leveling

Explanation

Resource leveling shifts noncritical activities within their float so labor demand is more even. Crashing shortens activities by adding resources, and front loading refers to billing, not scheduling.