A releasing system submittal is under review. Which item is most important to include?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2040
- B: A sequence of operation covering detection, time delay, abort and release
Explanation
Releasing systems need a clear sequence of operation so the reviewer can confirm detection logic, pre-discharge notification, time delay, abort and manual release. It also guides acceptance testing.
More questions: Submittals, Shop Drawings and Records
- 2001You are reviewing a fire alarm submittal before it goes to the building official. Which item does the IBC require on fire alarm shop drawings?
- 2002A submittal shows strobe locations but no candela settings. Under the IBC shop drawing requirements, how should the reviewer respond?
- 2003Under NFPA 72, which item belongs to the minimum documentation required for every new system?
- 2004Which format does NFPA 72 accept for the sequence of operation in the system documentation?
- 2005You are approving shop drawings drawn by a Level II technician. Which check is most important to confirm the drawings meet NFPA 72 documentation rules?
- 2006A reviewer stamps shop drawings with a status that lets the contractor proceed, provided the marked corrections are made, without a resubmittal. Which status is this?