Question 2074 of 299 · NICET Fire Alarm Systems Level I

During the annual test of a horn/strobe circuit, what should the technician verify?

Exactly one answer is correct.

Show solution

Correct answer to question 2074

  • C: Each appliance operates and strobes in view are synchronized

Explanation

Every appliance on the circuit must operate. Where several strobes are in view, they should flash in sync. Problems such as a dead appliance or out-of-sync strobes are recorded and fixed.