Question 2063 of 344 · NICET Fire Alarm Systems Level II

During an annual test, the panel is switched from primary to secondary power. What should be verified?

Exactly one answer is correct.

Show solution

Correct answer to question 2063

  • D: It runs on batteries and transfers back correctly

Explanation

Disconnecting primary power confirms that secondary power takes over, a trouble signal is produced, and the system transfers back when power is restored, with the charger recharging the batteries.