Question 4019 of 344 · NICET Fire Alarm Systems Level II
Under AIA A201 (2017), how long is the correction period after substantial completion?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4019
- A: 1 year
Explanation
If work is found not in accordance with the contract documents within one year after substantial completion, the contractor must correct it promptly after notice from the owner.
More questions: Management and Supervision
- 4020Under AIA A201 (2017), who is solely responsible for construction means, methods, techniques, sequences, and procedures?
- 4021Under AIA A201 (2017), what may the architect do with a submittal that the contract documents do not require?
- 4022A Level II technician finds a conflict between the fire alarm drawings and the ceiling plan. What is the correct way to resolve it?
- 4023Before acceptance testing of elevator recall and shunt trip, which coordination is needed?
- 4024On a new building, which trade usually installs the sprinkler waterflow and tamper switches that the fire alarm contractor then wires?
- 4025Smoke detectors are installed while drywall sanding is still going on. What should the supervisor arrange?