Question 4019 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), how long is the correction period after substantial completion?

Exactly one answer is correct.

Show solution

Correct answer to question 4019

  • A: 1 year

Explanation

If work is found not in accordance with the contract documents within one year after substantial completion, the contractor must correct it promptly after notice from the owner.

Next to question ›