A Level II technician finds a conflict between the fire alarm drawings and the ceiling plan. What is the correct way to resolve it?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4022
- C: Submit a request for information through the proper channel
Explanation
Conflicts are resolved through a written request for information to the designer or architect. The answer is documented and, if needed, reflected in revised drawings.
More questions: Management and Supervision
- 4023Before acceptance testing of elevator recall and shunt trip, which coordination is needed?
- 4024On a new building, which trade usually installs the sprinkler waterflow and tamper switches that the fire alarm contractor then wires?
- 4025Smoke detectors are installed while drywall sanding is still going on. What should the supervisor arrange?
- 4026Under the International Fire Code, a required fire alarm system is out of service. What must happen?
- 4027On a project schedule, what is the critical path?
- 4028A wire takeoff from the drawings measures 2,400 ft of cable. The supervisor adds 10 percent for waste and routing. How much cable should be ordered?