Question 4021 of 344 · NICET Fire Alarm Systems Level II
Under AIA A201 (2017), what may the architect do with a submittal that the contract documents do not require?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4021
- C: Return it without action
Explanation
Submittals not required by the contract documents may be returned by the architect without action. Only required submittals are reviewed.
More questions: Management and Supervision
- 4022A Level II technician finds a conflict between the fire alarm drawings and the ceiling plan. What is the correct way to resolve it?
- 4023Before acceptance testing of elevator recall and shunt trip, which coordination is needed?
- 4024On a new building, which trade usually installs the sprinkler waterflow and tamper switches that the fire alarm contractor then wires?
- 4025Smoke detectors are installed while drywall sanding is still going on. What should the supervisor arrange?
- 4026Under the International Fire Code, a required fire alarm system is out of service. What must happen?
- 4027On a project schedule, what is the critical path?