Question 4021 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), what may the architect do with a submittal that the contract documents do not require?

Exactly one answer is correct.

Show solution

Correct answer to question 4021

  • C: Return it without action

Explanation

Submittals not required by the contract documents may be returned by the architect without action. Only required submittals are reviewed.