Question 4020 of 344 · NICET Fire Alarm Systems Level II

Under AIA A201 (2017), who is solely responsible for construction means, methods, techniques, sequences, and procedures?

Exactly one answer is correct.

Show solution

Correct answer to question 4020

  • B: The contractor

Explanation

The contractor controls and is responsible for means, methods, techniques, sequences, and procedures, and for coordinating all parts of the work.