Question 4020 of 344 · NICET Fire Alarm Systems Level II
Under AIA A201 (2017), who is solely responsible for construction means, methods, techniques, sequences, and procedures?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4020
- B: The contractor
Explanation
The contractor controls and is responsible for means, methods, techniques, sequences, and procedures, and for coordinating all parts of the work.
More questions: Management and Supervision
- 4021Under AIA A201 (2017), what may the architect do with a submittal that the contract documents do not require?
- 4022A Level II technician finds a conflict between the fire alarm drawings and the ceiling plan. What is the correct way to resolve it?
- 4023Before acceptance testing of elevator recall and shunt trip, which coordination is needed?
- 4024On a new building, which trade usually installs the sprinkler waterflow and tamper switches that the fire alarm contractor then wires?
- 4025Smoke detectors are installed while drywall sanding is still going on. What should the supervisor arrange?
- 4026Under the International Fire Code, a required fire alarm system is out of service. What must happen?