Question 1034 of 297 · NICET Fire Alarm Systems Level III

What portion of a new fire alarm system must be tested during initial acceptance testing?

Exactly one answer is correct.

Show solution

Correct answer to question 1034

  • A: 100 percent of all devices, appliances, and functions

Explanation

Initial acceptance testing covers every device, appliance, circuit, and function of the new system. Sampling is allowed only in specific reacceptance situations. The Level III should make sure the contractor pretest covers everything before the AHJ witness test.