Question 1052 of 297 · NICET Fire Alarm Systems Level III

What must be done when testing of a monitored system is finished for the day?

Exactly one answer is correct.

Show solution

Correct answer to question 1052

  • C: Notify the same parties that testing has ended and confirm the system is back to normal

Explanation

Testing notifications work both ways: at the end, everyone who was told about the test is told it is finished. The system must be restored to normal, with no bypassed points or disabled outputs left behind.

Next to question ›