Question 2053 of 297 · NICET Fire Alarm Systems Level III

A building's fire alarm communicator was converted to an IP path with cellular backup. What must be verified during the annual test?

Exactly one answer is correct.

Show solution

Correct answer to question 2053

  • A: That each communication path works and its failure is reported as trouble

Explanation

With multiple paths, each path must be tested and a failure of any path must be annunciated at the premises and the supervising station within the times NFPA 72 specifies. Testing only one path can leave a silent failure on the other.

Next to question ›