Question 4019 of 297 · NICET Fire Alarm Systems Level III
Under AIA A201, who is solely responsible for construction means, methods, techniques, sequences, and procedures?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4019
- A: The Contractor
Explanation
A201 3.3.1 makes the Contractor solely responsible for, and in control of, construction means, methods, techniques, sequences, and procedures, unless the Contract Documents give other specific instructions.
More questions: Management and Supervision
- 4020Under AIA A201, are shop drawings part of the Contract Documents?
- 4021Under AIA A201, what must the Contractor do before sending shop drawings to the Architect?
- 4022Under AIA A201, what is a Change Order?
- 4023Under AIA A201, what is a Construction Change Directive?
- 4024Under AIA A201, the Architect orders a minor change in the work that does not affect cost or time. What is this called?
- 4025Under AIA A201, how long after Substantial Completion must the Contractor generally correct work found not to conform?