Question 4021 of 297 · NICET Fire Alarm Systems Level III

Under AIA A201, what must the Contractor do before sending shop drawings to the Architect?

Exactly one answer is correct.

Show solution

Correct answer to question 4021

  • A: Review and approve them, checking field dimensions

Explanation

A201 3.12.5 requires the Contractor to review, approve, and submit shop drawings, which represents that it has checked field measurements and coordinated the information with the Contract Documents.

Next to question ›