Question 4021 of 297 · NICET Fire Alarm Systems Level III
Under AIA A201, what must the Contractor do before sending shop drawings to the Architect?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4021
- A: Review and approve them, checking field dimensions
Explanation
A201 3.12.5 requires the Contractor to review, approve, and submit shop drawings, which represents that it has checked field measurements and coordinated the information with the Contract Documents.
More questions: Management and Supervision
- 4022Under AIA A201, what is a Change Order?
- 4023Under AIA A201, what is a Construction Change Directive?
- 4024Under AIA A201, the Architect orders a minor change in the work that does not affect cost or time. What is this called?
- 4025Under AIA A201, how long after Substantial Completion must the Contractor generally correct work found not to conform?
- 4026Under AIA A201, how soon must a Claim be made after the claimant first recognizes the condition giving rise to it?
- 4027Under AIA A201, what should the Contractor do on discovering an error between the drawings and specifications?