Question 4022 of 297 · NICET Fire Alarm Systems Level III

Under AIA A201, what is a Change Order?

Exactly one answer is correct.

Show solution

Correct answer to question 4022

  • D: A written change signed by all three parties on scope, cost, and time

Explanation

A201 7.2 defines a Change Order as a written instrument signed by the Owner, Contractor, and Architect stating agreement on the change in work, the amount of adjustment in Contract Sum, and the adjustment in Contract Time.

Next to question ›