Under AIA A201, what is a Construction Change Directive?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4023
- B: An Owner and Architect order to proceed before cost is agreed
Explanation
A201 7.3 allows the Owner and Architect to issue a Construction Change Directive directing a change in the work before agreement on adjustments. The Contractor proceeds, and cost and time are settled later.
More questions: Management and Supervision
- 4024Under AIA A201, the Architect orders a minor change in the work that does not affect cost or time. What is this called?
- 4025Under AIA A201, how long after Substantial Completion must the Contractor generally correct work found not to conform?
- 4026Under AIA A201, how soon must a Claim be made after the claimant first recognizes the condition giving rise to it?
- 4027Under AIA A201, what should the Contractor do on discovering an error between the drawings and specifications?
- 4028Under AIA A201, what does Substantial Completion mean?
- 4029A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?