Question 1039 of 243 · NICET Fire Alarm Systems Level IV

When a fire alarm contractor's project manager plans a large project, why is a schedule of values submitted early in the job?

Exactly one answer is correct.

Show solution

Correct answer to question 1039

  • B: It breaks the contract sum into line items that are used to measure progress for monthly payment

Explanation

A schedule of values allocates the contract amount among parts of the work, such as rough in, devices, programming and testing. Each pay application reports percent complete against those lines. A front loaded schedule of values is a red flag for the owner.

Next to question ›