When a fire alarm contractor's project manager plans a large project, why is a schedule of values submitted early in the job?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1039
- B: It breaks the contract sum into line items that are used to measure progress for monthly payment
Explanation
A schedule of values allocates the contract amount among parts of the work, such as rough in, devices, programming and testing. Each pay application reports percent complete against those lines. A front loaded schedule of values is a red flag for the owner.
More questions: Installation, Planning and Maintenance Management
- 1040A project manager is told a key activity on the critical path will finish 5 days late. Which response directly protects the project completion date?
- 1041Which closeout item gives the owner the narrative description of the system, operator instructions and the procedures for routine maintenance and testing?
- 1042A construction manager asks when the fire alarm contractor's warranty period normally starts. What is the most common contract answer?
- 1043At the acceptance test for a new voice evacuation system, the contractor should already have completed which step?
- 1044A cost report shows a job is 50 percent complete, with 62,000 dollars spent against a 110,000 dollar total cost budget. What is the projected cost at completion if the overrun rate continues?
- 1045Which business record should a fire alarm department manager review to compare the estimated and actual labor hours for each completed project?