A project manager is told a key activity on the critical path will finish 5 days late. Which response directly protects the project completion date?

Exactly one answer is correct.

Show solution

Correct answer to question 1040

  • B: Crash or fast track a later critical activity by adding resources or overlapping work

Explanation

Only shortening critical activities recovers the completion date. Adding resources to an activity with float does nothing for the end date. Crashing means adding resources to shorten duration, and fast tracking means overlapping activities that were sequential.