Question 1052 of 243 · NICET Fire Alarm Systems Level IV
In what order do the phases of a typical fire protection commissioning process occur?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1052
- D: Planning, design, construction, acceptance, post acceptance
Explanation
Commissioning starts early with planning and the OPR, follows through design and construction, ends with acceptance testing and continues into post acceptance with training and periodic testing. Starting commissioning only at construction loses much of its value.
More questions: Installation, Planning and Maintenance Management
- 1053Before the integrated test of a high-rise, what should have been completed for each individual system, such as the fire alarm, sprinkler and smoke control systems?
- 1054What must the record drawings delivered at closeout reflect?
- 1055Your field crew relocated 18 strobes during construction to avoid ductwork. Who is normally responsible for showing these changes on the record drawings?
- 1056A project manager wants the field changes captured accurately for record drawings. Which practice works best?
- 1057Which of these items is normally part of the fire alarm closeout package delivered to the owner?
- 1058At substantial completion of a fire alarm project, what condition normally applies?