A senior PM includes 8 percent contingency in a project budget. What is the purpose of that line?

Exactly one answer is correct.

Show solution

Correct answer to question 1065

  • A: To cover identified risks and costs that are likely but not yet defined

Explanation

Contingency is a reserve for risk, such as hidden conditions in a retrofit or price increases. Profit and approved change orders are separate line items. Tracking contingency use shows whether the risk assessment was realistic.