Question 1065 of 243 · NICET Fire Alarm Systems Level IV
A senior PM includes 8 percent contingency in a project budget. What is the purpose of that line?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1065
- A: To cover identified risks and costs that are likely but not yet defined
Explanation
Contingency is a reserve for risk, such as hidden conditions in a retrofit or price increases. Profit and approved change orders are separate line items. Tracking contingency use shows whether the risk assessment was realistic.
More questions: Installation, Planning and Maintenance Management
- 1066Your network shows two technicians needed in week 6 and seven in week 7 for the same project. What scheduling technique smooths these peaks within available float?
- 1067Which item should a fire alarm project manager order immediately after contract award because its lead time often controls the schedule?
- 1068Before installing devices, why must the shop drawings for a new system normally be approved?
- 1069A fire alarm system must recall elevators, close smoke dampers, release doors and shut down air handlers. Which coordination tool should be agreed with the mechanical, elevator and door hardware trades early in the project?
- 1070A company is invited to bid a design build fire alarm upgrade. What is the most important step before preparing the price?
- 1071In a proposal for a retrofit, why should the contractor list clarifications and exclusions?