Question 1002 of 243 · NICET Fire Alarm Systems Level IV
On a commissioning project, which document is written by the design team to explain how the owner's project requirements will be met, including code basis, assumptions and system descriptions?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1002
- D: The basis of design (BOD)
Explanation
The owner states goals and expectations in the OPR. The design team answers with the basis of design, which documents codes used, design assumptions and how each requirement is satisfied. The record of completion is prepared at the end of installation, not during design.
More questions: Installation, Planning and Maintenance Management
- 1003Under the commissioning process described in NFPA 3, who normally develops the owner's project requirements (OPR)?
- 1004Six addressable smoke detectors are added to an existing loop, and the program is edited to map them to an existing elevator recall output. What reacceptance testing is required?
- 1005After a change to site-specific software, NFPA 72 requires testing of all functions known to be affected by the change. What additional sample of initiating devices not directly affected must also be tested?
- 1006Under NFPA 72, who is responsible for the inspection, testing and maintenance of a fire alarm system and its interconnected emergency control functions?
- 1007You are setting up an ITM program for a 40 story office tower. How often must sensitivity of the spot-type smoke detectors be checked after the first year test, assuming each result stays within the listed range?
- 1008In the ITM schedule you are building, how often must waterflow alarm devices and valve supervisory switches be functionally tested?