Question 1002 of 243 · NICET Fire Alarm Systems Level IV

On a commissioning project, which document is written by the design team to explain how the owner's project requirements will be met, including code basis, assumptions and system descriptions?

Exactly one answer is correct.

Show solution

Correct answer to question 1002

  • D: The basis of design (BOD)

Explanation

The owner states goals and expectations in the OPR. The design team answers with the basis of design, which documents codes used, design assumptions and how each requirement is satisfied. The record of completion is prepared at the end of installation, not during design.

Next to question ›