Question 1100 of 243 · NICET Fire Alarm Systems Level IV
Which scheduling format shows each activity as a horizontal bar against a calendar, but does not clearly show the logic links between activities?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1100
- B: A bar chart, also called a Gantt chart
Explanation
Bar (Gantt) charts are easy to read for crews and owners but hide dependencies, so the effect of one delay on later work is not obvious. Network diagrams used in CPM show the logic and allow float calculations.
More questions: Installation, Planning and Maintenance Management
- 1001A hospital addition ties a new fire alarm network node into the existing campus system, smoke control, elevator recall and door release. Which document governs the testing that proves these interconnected systems work together as intended?
- 1002On a commissioning project, which document is written by the design team to explain how the owner's project requirements will be met, including code basis, assumptions and system descriptions?
- 1003Under the commissioning process described in NFPA 3, who normally develops the owner's project requirements (OPR)?
- 1004Six addressable smoke detectors are added to an existing loop, and the program is edited to map them to an existing elevator recall output. What reacceptance testing is required?
- 1005After a change to site-specific software, NFPA 72 requires testing of all functions known to be affected by the change. What additional sample of initiating devices not directly affected must also be tested?
- 1006Under NFPA 72, who is responsible for the inspection, testing and maintenance of a fire alarm system and its interconnected emergency control functions?