Question 2022 of 299 · NICET Fire Alarm Systems Level I

After a new device is installed on an existing system, what testing is required?

Exactly one answer is correct.

Show solution

Correct answer to question 2022

  • C: A reacceptance test of the new device and the functions it affects

Explanation

When devices are added or replaced, the new devices and any functions affected by them must be tested (reacceptance testing). A full building test is not normally required for one device.