Question 2090 of 299 · NICET Fire Alarm Systems Level I
During acceptance testing of a Class A initiating circuit, how is the redundant path proven?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2090
- B: Open the circuit at a point and confirm devices on both sides still alarm
Explanation
For Class A and Class X circuits, an open is introduced and the technician verifies that the panel shows a trouble and that devices beyond the open can still send an alarm.
More questions: Maintenance (Periodic Testing, Repair and Replacement)
- 2091How is ground fault supervision of a circuit verified during acceptance testing?
- 2092Within what time must a battery charger be able to recharge fully discharged fire alarm batteries?
- 2093A smoke detector is marked with a listed sensitivity range of 1.0 to 3.5 percent per foot obscuration. The test reads 3.9 percent per foot. What does this mean?
- 2094An addressable panel prints sensitivity readings for every smoke detector. May this be used for the required sensitivity test?
- 2095What qualification does NFPA 72 expect from people who inspect, test and maintain fire alarm systems?
- 2096Which statement about a Level I trainee performing tests is true?